Construction Updates

 

Visit this page for construction and related notices for work occurring in San Dimas.

Note that while the City makes every attempt to provide you with the most up-to-date information, construction schedules may change with little or no notice for various reasons, including, but not limited to, weather conditions and unforeseen delays.

Thank you for your patience as we work together to improve the City of San Dimas!

Please click here to visit the Caltrans website to check for traffic delays for the I-10 and other locations.

Click here to view recently completed projects.

 

CC2019-01 Rennell Et Al Street Improvement Project

 

Rennell Et Al Street Improvement Project

CC2019-01 Rennell Et Al Street Improvement Project

 

Rennell Et Al (Highlighted; Click image to enlarge)

 CC2019-01 Rennell Et Al Street Improvement Project includes the rehabilitation and resurfacing of Rennell Avenue from Juanita Avenue to Eaton Road, as well as Dunning Way, North Braziliana Drive, Saint George Drive from Rennell Avenue to Lone Hill Avenue, and Chaucer Court.

The project consists of 145,000 square feet of pavement repairs using approximately 2900 tons of asphalt concrete. 16 ADA accessible ramps within the project boundaries will be updated to current standards. This project also includes minor curb, gutter, and sidewalk repairs. Existing speed humps will be reconstructed as part of the project. Street paving will utilize rubberized asphalt material that is proven to be more durable and reclaims approximately 2900 used California tires that would otherwise be placed in a landfill.

The estimated project cost is $500,000, and of that cost, $196,000 is SB 1 (Gas Tax) funded. Other funding includes various Residential Street (Measure R) and general funds.

Project Update:

  • For the week Starting June 3, the contractor will complete the first coat of project traffic striping and start punch list items.
  • For the week of May 27, construction is scheduled to include finishing project paving, replacing speed humps, installing traffic loops and raising utility valves and manholes to grade. Pending weather the contractor is scheduled to place asphalt on Tuesday, May 28 and Wednesday, May 29. No construction will take place on Monday, May 27 in observance of Memorial Day.
  • For the week of May 20, the contractor will finish construction of ADA accessible ramps, and sidewalk repairs. The contractor will begin paving operations this Monday including cold milling existing pavement and placement of new asphalt pavement.
  • The contractor will place concrete for the construction of ADA accessible ramps, and sidewalk repairs this Saturday, May 18. Working hours for Saturday, May 18 are scheduled to start at 8 am and finish by 5 pm.
  • For the week of May 13, the contractor will start construction of ADA accessible ramps, sidewalk and curb and gutter repairs including the removal of existing concrete, formwork and placement of new concrete.
  • For the week of May 27, construction is scheduled to include finishing project paving, replacing speed humps, installing traffic loops and raising utility valves and manholes to grade. Pending weather the contractor is scheduled to place asphalt on Tuesday, May 28 and Wednesday, May 29. No construction will take place on Monday, May 27 in observance of Memorial Day.
  • For the week of May 20, the contractor will finish construction of ADA accessible ramps, and sidewalk repairs. The contractor will begin paving operations this Monday including cold milling existing pavement and placement of new asphalt pavement.
  • The contractor will place concrete for the construction of ADA accessible ramps, and sidewalk repairs this Saturday, May 18. Working hours for Saturday, May 18 are scheduled to start at 8:00 am and finish by 5 pm.
  • For the week of May 13, the contractor will start construction of ADA accessible ramps, sidewalk and curb and gutter repairs including the removal of existing concrete, formwork and placement of new concrete.
  • For the week of May 13, the contractor will start construction of ADA accessible ramps, sidewalk and curb and gutter repairs including the removal of existing concrete, formwork and placement of new concrete.
  • The contractor will place concrete for the construction of ADA accessible ramps and sidewalk repairs Saturday, May 18.  Work is scheduled to begin at 8:00 a.m. and end by 5:00 p.m.
  • For the week of May 20, the contractor will finish construction of ADA accessible ramps and sidewalk repairs.  Paving operations are scheduled to begin Monday, May 20, this will include cold milling existing pavement and placement of new asphalt pavement.

For any questions or concerns related to this project please contact the Public Works Department at (909) 394-6240 or publicworks@sandimasca.gov

 

The Gas Company – Kittering Road Gas Main and Services Replacement

 

The Gas Company – Kittering Road Gas Main and Services Replacement

The Gas Company – Kittering Road Gas Main and Services Replacement

 

*Click image to enlarge*

 

Southern California Gas Company has announced that the utility, which provides natural gas to Los Angeles County residents, is in the process of replacing over 1500 feet of gas main on Kittering Road at West Cypress Avenue and upgrading 46 residential services that connect to this section of the gas main. This work began in April and is expected to be completed by the end of the summer 2019.

 

Southern California Gas Company or its contractor Tiechert Pipelines may be visiting customers to let them know the inspections are taking place. In some cases, they may leave a letter to let customers know they are doing the work. If they cannot access the property, they will leave a door tag with information.  For more information please contact Southern California Gas Company at (877) 238-0092.

 

 

Translate
X